KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package III- Restoration of road damaged by laying pipelines along NH 183 (MC Road) on both sides in Kottayam Municipal area under NH Roads Division, Kollam
Project |
KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package III- Restoration of road damaged by laying pipelines along NH 183 (MC Road) on both sides in Kottayam Municipal area under NH Roads Division, Kollam |
Project Code |
KTMKIIFB0117545P4 |
Type |
Package |
Main Project |
KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
This package forms the road restoration part for pipe laying works under Package II along MC Road from Mariyapally to Kodimatha NH 183 under NH Roads Division,Kollam |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
19166600 |
TS Number |
TS/2021-2022/2021/14245 |
Technical specification |
Restoring the NH 183 road to BM/BC standards after pipe laying as per MoRD /MoRTH specifications |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
01/09/2021 |
Scheduled date of Completion as per agreement |
16 Dec 2021 |
Expected date of Completion |
31/12/2023 |
Processing Dates
TS Date |
25 Jun 2021 |
Estimate Approval |
25 Jun 2021 |
NIT Approval |
29 Jun 2021 |
Tender Closing |
23 Jul 2021 |
Technichal Pre-Qualification |
06 Aug 2021 |
Price bid opening |
06 Aug 2021 |
Approval Dates
Workorder Date |
17 Aug 2021 |
NA |
01 Sep 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kottayam Proj Dn AE4 |
Date: 20/04/2024 |
Work has started | 0% Completed
This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started.Hence decided to foreclose the work.
.
Kottayam Proj Dn AE4 |
Date: 20/03/2024 |
Work has started | 0% Completed
This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started.Hence decided to foreclose the work.
.