| Project | DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara |
|---|---|
| Project Code | IDKGOK112213313P1 |
| Type | Package |
| Main Project | DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Marykulam-Nariyampara |
| Funding Agency | GOK |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DEPOSIT-KRFB-Hill Highway KRFB-2017-2018-Improvements to Permed, Devikulam Road KM 19/000 to 40/050 and Thodupuzha - Puliyanmala road KM 85/500 to 92/167 in Idukki dist Marykulam-Nariyampara - Shifting of KWA utilities Pipeline work |
| Status | On-going |
| District | Idukki |
| Executing Office | Kattappana Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 27860000 |
| TS Number | WRD/KWA-CE(CR)/EST_TS/12798/2022_26_1_1 |
| Technical specification | Utility shifting - Pipeline work Supply of DI K9 Pipe 250mm- 600m PVC Pipe, 10kg/cm2, 200mm Dia- 2884m PVC Pipe, 10kg/cm2, 160mm Dia- 4686m PVC Pipe, 10kg/cm2, 90mm Dia- 3920m 80mm GI Medium Pipe- 560m 150mm GI medium pipe- 42m |
| Contractor | BOBBY KURIAN (Mob: 9388758835) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 16/01/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Dec 2024 |
| Expected date of Completion | 30/12/2024 |
| TS Date | 09 Dec 2022 |
|---|---|
| Estimate Approval | 09 Dec 2022 |
| NIT Approval | 27 Dec 2022 |
| Tender Closing | 08 Apr 2023 |
| Price bid opening | 29 Dec 2022 |
| Workorder Date | 09 Jan 2023 |
|---|---|
| NA | 12 Jan 2023 |
| Kattappana AEE 1 |
| Date: 29/01/2026 |
Work has been completed | 100% Completed
COMPLETED.
| Kattappana AEE 1 |
| Date: 28/01/2026 |
Work in progress | 99% Completed
So far laid 3570.5 metres of 90mm PVC pipe, 4686 metres of 160 mm PVC pipe, 78.5 metres of 200mm DI, 2955 metres of 200mm PVC pipe, 558 metres of 80mm GI pipe, 619 metres of 250mm DI, 106.15 metres of 200mm MS, 15.55 metres of 250mm MS and 276.04 metres of 150mm GI pipe. Total laid 12645.54 m out of 12692 m View all updates.