KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths-Package 2 - Construction & Commissioning of 45 MLD WTP, 44 LL OHSR, 25 LL Sump, Supply, laying, commissioning 450 mm dia DI K9 CWPM.

Project KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths-Package 2 - Construction & Commissioning of 45 MLD WTP, 44 LL OHSR, 25 LL Sump, Supply, laying, commissioning 450 mm dia DI K9 CWPM.
Project Code MLPKIIFB0117518P2
Type Package
Main Project KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Design construction commissioning of 45 MLD WTP ,44LL OHSR, 25 LL sump, 450mm DI k9 CWPM-62.6m Package Cost - 338769722.00 Over run by - 4 months 9 days
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 338769722
TS Number GO (Rt) No.14/2017/WRD dtd 11/1/2017
Technical specification Design construction commissioning of 45 MLD WTP ,44LL OHSR, 25 LL sump, 450mm DI k9 CWPM-62.6m Package Cost - 338769722.00

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Nov 2021 Pending Pending Risks From Other Projects The Project production components have been completed. Laying KSEB dedicated feeder line to RWP is arranged as deposit to KSEB. They have started work by 01-10-21 however the work is halted due to non availability of KSEB department supplied items like A-pole, ABC Cable etc. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/11/2017
Scheduled date of Completion as per agreement 31 Mar 2023
Expected date of Completion 31/12/2021

Processing Dates

TS Date 19 Jan 2017
Estimate Approval 19 Jan 2017
NIT Approval 05 May 2017
Tender Closing 20 Oct 2017
Technichal Pre-Qualification 01 Aug 2017
Price bid opening 01 Aug 2017

Approval Dates

Workorder Date 23 Oct 2017
NA 24 Oct 2017

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE5
Date: 04/05/2024

Work in progress | 98% Completed

Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. .

Malappuram Project Dn AE5
Date: 03/05/2024

Work in progress | 98% Completed

Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. .