- Home
- KIIFB special Investment package - WRD01...
KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths-Package 2 - Construction & Commissioning of 45 MLD WTP, 44 LL OHSR, 25 LL Sump, Supply, laying, commissioning 450 mm dia DI K9 CWPM.
Project |
KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths-Package 2 - Construction & Commissioning of 45 MLD WTP, 44 LL OHSR, 25 LL Sump, Supply, laying, commissioning 450 mm dia DI K9 CWPM. |
Project Code |
MLPKIIFB0117518P2 |
Type |
Package |
Main Project |
KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Design construction commissioning of 45 MLD WTP
,44LL OHSR,
25 LL sump,
450mm DI k9 CWPM-62.6m
Package Cost - 338769722.00
Over run by - 4 months 9 days |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
338769722 |
TS Number |
GO (Rt) No.14/2017/WRD dtd 11/1/2017 |
Technical specification |
Design construction commissioning of 45 MLD WTP
,44LL OHSR,
25 LL sump,
450mm DI k9 CWPM-62.6m
Package Cost - 338769722.00 |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
01 Nov 2021 |
Pending |
Pending |
Risks From Other Projects |
The Project production components have been completed. Laying KSEB dedicated feeder line to RWP is arranged as deposit to KSEB. They have started work by 01-10-21 however the work is halted due to non availability of KSEB department supplied items like A-pole, ABC Cable etc. |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
23/11/2017 |
Scheduled date of Completion as per agreement |
31 Mar 2023 |
Expected date of Completion |
31/12/2021 |
Processing Dates
TS Date |
19 Jan 2017 |
Estimate Approval |
19 Jan 2017 |
NIT Approval |
05 May 2017 |
Tender Closing |
20 Oct 2017 |
Technichal Pre-Qualification |
01 Aug 2017 |
Price bid opening |
01 Aug 2017 |
Approval Dates
Workorder Date |
23 Oct 2017 |
NA |
24 Oct 2017 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn AE5 |
Date: 04/05/2024 |
Work in progress | 98% Completed
Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate.
.
Malappuram Project Dn AE5 |
Date: 03/05/2024 |
Work in progress | 98% Completed
Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate.
.