- Home
- Jal Jeevan Mission -Phase I-BAWSS to Kun...
Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath
Project |
Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath |
Project Code |
KLMJJM08204250 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) |
Status |
On-going |
District |
Kollam |
Executing Office |
Kundara PH Sn |
AS Amount (Rs) |
152500000
|
AS Number |
GO(Rt)no.541/2020/WRD |
TS Amount (Rs) |
87300000 |
TS Number |
7575/2020-2021 |
Total Bill Submitted (Rs) |
50553671 |
Total Bill Paid (Rs) |
45678624 |
Population Benefitted |
15600 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
31 Jan 2022 |
Coverage |
Kundara panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath |
Kundara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
work in progress |
Kundara PH Sn - AE |
|
19 Jun 2024 |
Work in progress |
Kundara PH Sn - AE |
|
19 Jun 2024 |
Work in progress |
Kundara PH Sn - AE |
|
18 Jun 2024 |
Work in progress |
Kundara PH Sn - AE |
|
15 Jun 2024 |
Work in progress |
Kundara PH Sn - AE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
17 May 2022 |
Pending |
Pending |
Road Cut Related Risk |
Kottarakkara Pulamon jn to Padinjarethruv |
No comments available. |
Pending |
17 May 2022 |
Pending |
Pending |
Road Cut Related Risk |
Kottarakkara Pulamon Jn. to Padinjare Theruv |
No comments available. |
Pending |
17 May 2022 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting - Kottarakkara pulamon jn to Padinjaretheruv |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
26/02/2021 |
Scheduled date of Completion of the Project |
06 Jan 2022 |
Expected date of Completion |
31/12/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
18 Sep 2020 |