Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath

Project Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath
Project Code KLMJJM08204250P1
Type Package
Main Project Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Description Jal Jeevan Mission -Phase I-BAWSS to Kundara and adjoining panchayaths- Providing house connection from existing pipe line, extension of pipe line and Replacement of pipe line and part of rennovation work in WTP(Elampal) in Kundara grama panchayath
Status On-going
District Kollam
Executing Office Kottarakkara PH Dn
TS Amount (Rs) 87300000
TS Number 7575/2020-2021
Technical specification Work in progress

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 26/02/2021
Scheduled date of Completion as per agreement 25 Feb 2023
Expected date of Completion 25/02/2023

Processing Dates

TS Date 18 Sep 2020
Estimate Approval 18 Sep 2020
NIT Approval 14 Jan 2021
Tender Closing 21 Jan 2021
Technichal Pre-Qualification 23 Jan 2021
Price bid opening 23 Jan 2021

Approval Dates

Workorder Date 05 Feb 2021
Agreement Date 26 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Kottarakkara PH Dn EE
Date: 24/07/2021

Work in progress | 17% Completed

Work is going on.

Kottarakkara PH Dn EE
Date: 23/07/2021

Work in progress | 17% Completed

Work is going on.