- Home
- JJM - NABL - Accreditation - Setting up...
JJM - NABL - Accreditation - Setting up of Quality Sub District Control Lab at Kollam - Kadakkal, Chadayamangalam
| Project |
JJM - NABL - Accreditation - Setting up of Quality Sub District Control Lab at Kollam - Kadakkal, Chadayamangalam |
| Project Code |
KLMJJM09218462 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
JJM - NABL - Accreditation - Setting up of Quality Sub District Control Lab at Kollam - Kadakkal, Chadayamangalam |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kollam QC Sn |
| AS Amount (Rs) |
11100000
|
| AS Number |
GO(Rt) No. 489/2021/WRD |
| TS Amount (Rs) |
3000000 |
| TS Number |
TS/2021-2022/2021/16785 |
| Total Bill Submitted (Rs) |
2289688 |
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
29 Mar 2022 |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
JJM - NABL - Accreditation - Setting up of Quality Sub District Control Lab at Kollam - Kadakkal, Chadayamangalam |
Kollam QC Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 17 Jun 2022 |
Work completed |
Kollam QC AE |
|
| 16 Apr 2022 |
Finishing work of physio chemical area in progress |
Kollam QC AE |
|
| 07 Apr 2022 |
Microbiology area brick work completed , roofing completed, Physical tile work in progres |
Kollam QC AE |
|
| 18 Mar 2022 |
Microbiology area brickwork in progress, physical/chemical area plumping work ongoing |
Kollam QC AE |
|
| 04 Mar 2022 |
new microbiology area foundation and brick work in progress. Physical/chemical area electrical work completed |
Kollam QC AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
21/11/2021 |
| Scheduled date of Completion of the Project |
20 Feb 2022 |
| Expected date of Completion |
Date is not specified |
Processing Dates
| AS Date |
18 Sep 2021 |
| TS Date |
22 Oct 2021 |