17 Jun 2022 Work completed Kollam QC AE
16 Apr 2022 Finishing work of physio chemical area in progress Kollam QC AE
07 Apr 2022 Microbiology area brick work completed , roofing completed, Physical tile work in progres Kollam QC AE
18 Mar 2022 Microbiology area brickwork in progress, physical/chemical area plumping work ongoing Kollam QC AE
04 Mar 2022 new microbiology area foundation and brick work in progress. Physical/chemical area electrical work completed Kollam QC AE
25 Feb 2022 Slab work, truss work completed electrical work ongoing Kollam QC AE
28 Jan 2022 Items shifting completed. Roof sheet work in progress. Slab work and demolishing work in progress Kollam QC AE
18 Jan 2022 Items stored at quarters is being shifted, roof sheeting work of physical/chemical lab is schedulded to start Kollam QC AE
10 Jan 2022 The current proposed site is shifted to the new site at of Madathara quarters due to shifting issue and space availability Kollam QC AE
06 Jan 2022 Work will start on 10/01/2022, shifting pipes and specials from site is scheduled Kollam QC AE