| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jun 2022 | Work completed | Kollam QC AE | |
| 16 Apr 2022 | Finishing work of physio chemical area in progress | Kollam QC AE | |
| 07 Apr 2022 | Microbiology area brick work completed , roofing completed, Physical tile work in progres | Kollam QC AE | |
| 18 Mar 2022 | Microbiology area brickwork in progress, physical/chemical area plumping work ongoing | Kollam QC AE | |
| 04 Mar 2022 | new microbiology area foundation and brick work in progress. Physical/chemical area electrical work completed | Kollam QC AE | |
| 25 Feb 2022 | Slab work, truss work completed electrical work ongoing | Kollam QC AE | |
| 28 Jan 2022 | Items shifting completed. Roof sheet work in progress. Slab work and demolishing work in progress | Kollam QC AE | |
| 18 Jan 2022 | Items stored at quarters is being shifted, roof sheeting work of physical/chemical lab is schedulded to start | Kollam QC AE | |
| 10 Jan 2022 | The current proposed site is shifted to the new site at of Madathara quarters due to shifting issue and space availability | Kollam QC AE | |
| 06 Jan 2022 | Work will start on 10/01/2022, shifting pipes and specials from site is scheduled | Kollam QC AE |