Project | KIIFB 2017-18 WRD 025-27:Augmentation of WSS to Karimpukayam-Package III |
---|---|
Project Code | KTMKIIFB1118571P3 |
Type | Package |
Main Project | KIIFB 2017-18-WRD 025-27- Karimpukayam Water supply project- Augmentation of ARWSS to Kanjirappally, Elikkulam and Chirakkadavu panchayat in Kottayam district |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | This package consists of following components: **350 mm DI K9 CWGM from OHSR at WTP to sump at Gramadeepam **Distribution network in Elikkulam Panchayath Zone 3B **2 LL sump at Gramadeepam Booster Pump House |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 260600000 |
TS Number | TS/2020-2021/2020/20420 |
Technical specification | This package consists of following components: 350 mm DI K9 CWGM from OHSR at WTP to sump at Gramadeepam Distribution network in Elikkulam Panchayath Zone 3B 2 LL sump at Gramadeepam Booster Pump House |
Contractor | K A Abraham (Mob: 9447715266) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Jan 2022 | Pending | Pending | Contract Related Risks | Works not started by Contractor | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/05/2021 |
---|---|
Scheduled date of Completion as per agreement | 03 May 2022 |
Expected date of Completion | 31/03/2023 |
TS Date | 02 Feb 2021 |
---|---|
Estimate Approval | 02 Feb 2021 |
NIT Approval | 12 Mar 2021 |
Tender Closing | 22 Mar 2021 |
Technichal Pre-Qualification | 08 Apr 2021 |
Price bid opening | 17 Apr 2021 |
Workorder Date | 04 May 2021 |
---|---|
NA | 28 Jun 2021 |
Kottayam Proj Dn AE4 |
Date: 09/04/2024 |
Work in progress | 1% Completed
The Risk & cost estimate prepared with revised SOR in Price 3.0. The stay order has to be vacated for WP(C) 14792/2022 filed by J&B Engineering (Judgement dated 29/04/2022 on WP(C) 14792/2022). .
Kottayam Proj Dn AE4 |
Date: 08/04/2024 |
Work in progress | 1% Completed
The Risk & cost estimate prepared with revised SOR in Price 3.0. The stay order has to be vacated for WP(C) 14792/2022 filed by J&B Engineering (Judgement dated 29/04/2022 on WP(C) 14792/2022). .