KIIFB 2017-18-WRD 025-27- Karimpukayam Water supply project- Augmentation of ARWSS to Kanjirappally, Elikkulam and Chirakkadavu panchayat in Kottayam district
Project |
KIIFB 2017-18-WRD 025-27- Karimpukayam Water supply project- Augmentation of ARWSS to Kanjirappally, Elikkulam and Chirakkadavu panchayat in Kottayam district |
Project Code |
KTMKIIFB1118571 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Augmentation of existing scheme.Augmentation consists of following components:
6 MLD WTP at Karimpukayam existing WTP premises.
500 MM DI K9 RWPM
400 MM DI K9 CWPM from sump to OHSR at WTP
6 LL OHSR at WTP site
5 LL OHSR at Panechapally
8.5 LL OHSR at Thambalakkadu
200 HP Raw water pump set
50 HP CW P/S to OHSR at WTP site
50 HP CW P/S to Panechapally
Power enhancement at Gramadeepam and WTP premises
Distribution network in Kanjirapally(Zone 1,2,3A),Chirakkadavu panchayath(Zone 1B,4 &5),Elikkulam Panchayath(Zone 3B)
75 HP P/S from Gramadeepm to Ponkunnam
10 HP P/S from Gramadeepm to Kanjirapally
120HP P/S from Gramadeepm to Thambalakkadu
RR charges
Cost of Land
2 ll sump at Gramadeepam,
350 mm DI K9 from OHSR at WTP to Gramadeepam
300 DI K9 CWPM from Gramadeepam to Thamabalakkadu
250 DI K9 CWPM from Gramadeepam to Ponkunnam
|
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
686400000
|
AS Number |
G.O(Rt) No 227/2018/WRD |
TS Amount (Rs) |
260600000 |
TS Number |
TS/2020-2021/2020/20420 |
Total Bill Submitted (Rs) |
1 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
90000 |
Capacity in MLD |
15.00 |
Actual Project Completion Date |
30 Nov 2022 |
Coverage |
Kanjirapally,Elikkulam and Chirakkadavu panchayaths of kanjirapally and Pala constituencies |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB 2017-18 WRD 025-27:Augmentation of WSS to Karimpukayam-Package I |
Kottayam Project Dn |
|
2 |
KIIFB 2017-18 WRD 025-27:Augmentation of WSS to Karimpukayam-Package II |
Kottayam Project Dn |
|
3 |
KIIFB 2017-18 WRD 025-27:Augmentation of WSS to Karimpukayam-Package III |
Kottayam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Nov 2023 |
Package 1-Regarding the handing over of the lands, meetings were conducted in the chamber of district collector, kottayam on 26/10/2022, 7/11/2022. As directed by the district collector, we have submitted the revised drawing for the 10cent land for 5LL OHSR at penechapally. The district collector has given direction to the LA Tahsildar (KIIFB) in order to fix the values for other two lands. The BVR for the 3 lands has to be issued from the Collectorate, 19(11) notification published on oct 2023. Award of land placed on 28.11.2023, after hand over of land works can be tendered
Package 2- Pipe laying works and pressure testing works in the Chirakkadavu zone 1B , Zone 4 & Zone 5 area in progress. PWD road cutting sanction pending on 1, Ponkunnam - Azheekkal road, 2, Kanjirapally- Elikulam road, 3, Chamampathal-Thekkethukavala, 4, 19th mile- Chirakadavu, 5, Mooleplavu- Powathukavala-Koombukkal purayidam. NH 183 cutting sanction pending on Ponkunnam- KVMS , process at NH division Muvattupuzha
Package 3- The Risk & cost estimate prepared with revised SOR in Price 3.0. The stay order has to be vacated for WP(C) 14792/2022 filed by J&B Engineering (Judgement dated 29/04/2022 on WP(C) 14792/2022).
|
Kottayam Proj Dn AE4 |
|
23 Jan 2023 |
Package I: Regarding the handing over of the lands, meetings were conducted in the chamber of district collector, kottayam on 26/10/2022, 7/11/2022. As directed by the district collector, we have submitted the revised drawing for the 10cent land for 5LL OHSR at penechapally. The district collector has given direction to the LA Tahsildar (KIIFB) in order to fix the values for other two lands. The BVR for the 3 lands has to be issued from the Collectorate. PACKGE 2 Pipe laying works and pressure testing works in the Chirakkadavu area in progress. package 3:The Risk & cost estimate prepared with revised SOR in Price 3.0. The stay order has to be vacated for WP(C) 14792/2022 filed by J&B Engineering (Judgement dated 29/04/2022 on WP(C) 14792/2022). |
Kottayam Proj Dn AE4 |
|
01 Aug 2022 |
Package I
Sub division sketch for 68 cent land is being prepared at LA Tahsildar office.On approval next step is 19(1) notification with submission of Basic Valuation Report.
PACKGE 2
Tender docs with price bid submitted to CE office for evaluation on 30.07.2022
PACKGE3
TS for risk and cost estimate is awarded.Maintained STATUS QUO vide order from high court |
Kottayam Proj Dn AE4 |
|
10 Jul 2022 |
PAkage 1 Final survey at site is completed on 24.06.2022 by LA Tahsildar,Vaikom.All obligations from KWA side is complete.On discussuion,it is understood that Basic Valuation Report is being prepared by Tahsildr and will submit soon to District Collector.Meanwhile to expedite the procees of land availability,seperate movement from Panchayath side is ongoing to handover the land by including in JJM projects.resolution is recieved. Package 2 Tendered. Package 3 Is send for TS as risk and cost estimate. |
Kottayam Proj Dn AE4 |
|
30 Jun 2022 |
PAkage 1
Final survey at site is completed on 24.06.2022 by LA Tahsildar,Vaikom.All obligations from KWA side is complete.On discussuion,it is understood that Basic Valuation Report is being prepared by Tahsildr and will submit soon to District Collector.Meanwhile to expedite the procees of land availability,seperate movement from Panchayath side is ongoing to handover the land by including in JJM projects.resolution is recieved.
Package 2
Tendered and due date is 19.6.22
Package 3
Is send for TS as risk and cost estimate. |
Kottayam Proj Dn AE4 |
|
Review Date |
Review Message |
Review Attended By |
11 Oct 2021 |
Please follow up with DC , also explore the possibility to get the land in advance possession in coordination with GP |
|
Duration & Sanction dates
Date of start of Project |
04/05/2021 |
Scheduled date of Completion of the Project |
31 Mar 2023 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
31 Mar 2018 |
TS Date |
31 Mar 2018 |