Project | JJM-CWSS to Idukki- Kanjikuzhi, Vazhathope, Mariyapuram, Kamakshi, Vathikudy and Vannapuram (Part) Panchayaths in Idukki District |
---|---|
Project Code | IDKJJM052210880 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-CWSS to Idukki- Kanjikuzhi, Vazhathope, Mariyapuram, Kamakshi, Vathikudy and Vannapuram (Part) Panchayaths in Idukki District |
Status | On-going |
District | Idukki |
Executing Office | Kattappana Project Dn |
AS Amount (Rs) | 4190030000 |
AS Number | G.O.(Rt)No.401/2022/WRD |
TS Amount (Rs) | 2722905160 |
TS Number | |
Total Bill Submitted (Rs) | 3116860 |
Total Bill Paid (Rs) | 3116860 |
Population Benefitted | 98362 |
Capacity in MLD | 35.00 |
Actual Project Completion Date | Date is not specified |
Coverage | Kanjikuzhi - 6992 FHTC's, Vannapuram - 2900 FHTC's, Mariyapuram - 1807 FHTC's, Kamakshi - 5015 FHTC's, Vathikudy - 5683FHTC's. |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | Package 10:supply and laying CWPM and GM and storage reservoir cum pump house in kamakshi panchayath | Project Division Kattapana | |
2 | Package 11:Construction of 2.5 Lakhs Litre capacity OH Tank at Painavu | Project Division Kattapana | |
3 | Package 12 - Construction of 35 MLD Water Treatment Plant | Project Division Kattapana | |
4 | Package 13 : Supply and laying CWPM and GM and Storage reservoir cum pump house in Mariyapuram Panchayth | Project Division Kattapana | |
5 | Package 14: Supply and laying CWGM and Construction of steel tanks at Vannapuram Panchayath | Project Division Kattapana | |
6 | Package 15:Supply and erection of Floating Pump and Raw water Pumping main | Project Division Kattapana | |
7 | Package 16: Control Room and Surveillance unit for Floating Pumping Station | Project Division Kattapana | |
8 | Package 17:Supply and erection of clear water pumpsets for WTP and other boosting stations | Project Division Kattapana | |
9 | Package 1- Survey and investigation works | Project Division Kattapana | |
10 | Package 2 - Supply and laying CWPM and GM With storage reservoir in Vathikudy panchayath. | Project Division Kattapana | |
11 | Package - 3 - Supply and laying distribution system and Providing FHTCs in Kanjikuzhi Panchayat | Project Division Kattapana | |
12 | Package 4 - Supplying and laying distribution system and Providing FHTCs in Kamakshi Panchayat | Project Division Kattapana | |
13 | Package 5 - Supply and laying distribution system in Mariyapuram panchayath and Providing FHTCs | Project Division Kattapana | |
14 | Package 6- Supply and laying distribution system and Providing FHTCs in Vannappuram Panchayath | Project Division Kattapana | |
15 | Package 7- Supply and laying distribution system and Providing FHTCs in Vathikudy panchayath | Project Division Kattapana | |
16 | Package 8:Urgent laying of 400mm DI K9 pipe in Cheruthoni Centre junction | Project Division Kattapana | |
17 | Package 9:Supply and laying CWPM and GM and storage reservoir cum pump house in Kanjikuzhi panchayath | Project Division Kattapana |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 May 2024 | package 1 Survey work and package 8 -completed , package 2 -48% completed, package 3 -17% completed , package 4 -55% completed, package 5 - 31% completed , package 6 - 18% completed , package 7-24% completed, package 9- 2% completed , package 10- not tendered, package 11 - site handover to contractor on 12/03/24, package 12-5% completed , package 13- not tendered. Package 14 7% completed, package 16 work awarded to district labour contract co-operative society package 17 LOA issued waiting for site getting ready, package 15 LOA issued on 06/12/23 | Kattappana AEE 1 | |
12 May 2024 | package 1 Survey work and package 8 -completed , package 2 -48% completed, package 3 -17% completed , package 4 -55% completed, package 5 - 31% completed , package 6 - 18% completed , package 7-24% completed, package 9- 2% completed , package 10- not tendered, package 11 - site handover to contractor on 12/03/24, package 12-5% completed , package 13- not tendered. Package 14 7% completed, package 16 work awarded to district labour contract co-operative society package 17 LOA issued waiting for site getting ready, package 15 LOA issued on 06/12/23 | Kattappana AEE 1 | |
11 May 2024 | package 1 Survey work and package 8 -completed , package 2 -48% completed, package 3 -17% completed , package 4 -55% completed, package 5 - 31% completed , package 6 - 18% completed , package 7-24% completed, package 9- 2% completed , package 10- not tendered, package 11 - site handover to contractor on 12/03/24, package 12-5% completed , package 13- not tendered. Package 14 7% completed, package 16 work awarded to district labour contract co-operative society package 17 LOA issued waiting for site getting ready, package 15 LOA issued on 06/12/23 | Kattappana AEE 1 | |
10 May 2024 | package 1 Survey work and package 8 -completed , package 2 -48% completed, package 3 -17% completed , package 4 -55% completed, package 5 - 31% completed , package 6 - 18% completed , package 7-24% completed, package 9- 2% completed , package 10- not tendered, package 11 - site handover to contractor on 12/03/24, package 12-5% completed , package 13- not tendered. Package 14 7% completed, package 16 work awarded to district labour contract co-operative society package 17 LOA issued waiting for site getting ready, package 15 LOA issued on 06/12/23 | Kattappana AEE 1 | |
09 May 2024 | package 1 Survey work and package 8 -completed , package 2 -48% completed, package 3 -17% completed , package 4 -55% completed, package 5 - 31% completed , package 6 - 18% completed , package 7-24% completed, package 9- 2% completed , package 10- not tendered, package 11 - site handover to contractor on 12/03/24, package 12-5% completed , package 13- not tendered. Package 14 7% completed, package 16 work awarded to district labour contract co-operative society package 17 LOA issued waiting for site getting ready, package 15 LOA issued on 06/12/23 | Kattappana AEE 1 |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
27 Mar 2023 | Pending | Pending | Road Cut Related Risk | Sabarimala - Kadaikkanal road (Blathikkavala- Melachinnar) [Antopuram - Murikkassery] | No comments available. | Pending |
27 Mar 2023 | Pending | Pending | Road Cut Related Risk | THOPRAMKUDI- NJARAKAVALA-ETTITHOPPU | No comments available. | Pending |
22 Mar 2023 | Pending | Pending | Road Cut Related Risk | NH-185 ADIMALY KUMILY(PANAMKUTTY TO ATTIKALAM) | No comments available. | Pending |
Date of start of Project | 29/04/2022 |
---|---|
Scheduled date of Completion of the Project | 29 Mar 2024 |
Expected date of Completion | 31/03/2025 |
AS Date | 13 May 2022 |
---|---|
TS Date | 29 Oct 2022 |
Project Officers | View |
---|