Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Jun 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
29 Jun 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
24 Jun 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
17 Jun 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
12 Jun 2021 | PWD Issued Demand notice for Pipe laying works | Pathanamthitta PH Dn EE | |
02 Jun 2021 | Joint Inspection with PWD Completed | Pathanamthitta PH Dn EE | |
18 May 2021 | Joint Inspection with PWD Completed | Pathanamthitta PH Dn EE | |
14 May 2021 | PWD Demanding Security deposit & Supervision charges to grand permission for starting the work, as the newly constructed road under DLP. | Pathanamthitta PH Dn EE | |
07 May 2021 | PWD Demanded Security deposit & Supervision charges - to grand permission for starting the work, as the DLP of the newly constructed road started. | Pathanamthitta PH Dn EE | |
19 Apr 2021 | PWD Demanded Security deposit & Supervision charges - to grand permission for starting the work, as the DLP of the newly constructed road started. | Pathanamthitta PH Dn EE |