Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 May 2022 | Interconnection work at Koothattukulam junction delayed due to public issues. | Pathanamthitta PH Dn EE | |
11 May 2022 | laying of of 150mm DI pipe progress (2km completed) | Pathanamthitta PH Dn EE | |
20 Feb 2022 | Work progressing Due to rock blasting laying of pipes taking more time | Pathanamthitta PH Dn EE | |
07 Feb 2022 | Work progressing Due to rock blasting laying of pipes taking more time | Pathanamthitta PH Dn EE | |
03 Feb 2022 | Work progressing Due to rock blasting laying of pipes taking more time | Pathanamthitta PH Dn EE | |
01 Feb 2022 | Work in progress | 18% Completed | Pathanamthitta PH Dn EE | |
05 Aug 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
25 Jul 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
18 Jul 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE | |
11 Jul 2021 | 15% work completed, awaiting Pipes & PWD Sanction for laying | Pathanamthitta PH Dn EE |