Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Dec 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - Side wall concreting | Edappal Sn AE | |
13 Dec 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - Concreting of raft foundation completed, Haunch concrete finished | Edappal Sn AE | |
11 Dec 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - Concreting of raft foundation completed, Haunch concrete finished | Edappal Sn AE | |
08 Dec 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - Concreting of raft foundation completed, Wall casting started | Edappal Sn AE | |
05 Dec 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - Concreting of raft foundation completed | Edappal Sn AE | |
01 Dec 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - Concreting of raft foundation and column | Edappal Sn AE | |
28 Nov 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - steel work started for raft foundation and column | Edappal Sn AE | |
24 Nov 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - steel work started for raft foundation | Edappal Sn AE | |
20 Nov 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - steel work started for raft foundation | Edappal Sn AE | |
16 Nov 2023 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - PCC work completed , curing period | Edappal Sn AE |