25 Nov 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab ongoing | Edappal Sn AE | |
21 Nov 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab ongoing | Edappal Sn AE | |
18 Nov 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab ongoing | Edappal Sn AE | |
11 Nov 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. | Edappal Sn AE | |
06 Nov 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting progressing. | Edappal PH Dn EE | |
02 Nov 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting progressing | Edappal Sn AE | |
29 Oct 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting progressing | Edappal Sn AE | |
23 Oct 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting progressing | Edappal Sn AE | |
18 Oct 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall bar bending work ongoing | Edappal Sn AE | |
09 Oct 2024 | 1. Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall bar bending work ongoing | Edappal Sn AE |