Jal Jeevan Mission(JJM)-JJM Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 2-Construction of 33LL Capacity Master OHSR at IDTR and 38LL Capacity GLSR at IDTR for Kaladi and Edappal Panchayaths
Jal Jeevan Mission(JJM)-JJM Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 2-Construction of 33LL Capacity Master OHSR at IDTR and 38LL Capacity GLSR at IDTR for Kaladi and Edappal Panchayaths
Project Code
MLPJJM022214980
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-01
Description
Jal Jeevan Mission(JJM)-JJM Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 2-Construction of 33LL Capacity Master OHSR at IDTR and 38LL Capacity GLSR at IDTR for Kaladi and Edappal Panchayaths
Status
On-going
District
Malappuram
Executing Office
Edappal PH Dn
AS Amount (Rs)
2331700000
AS Number
GO(Rt)No.134/2022/WRD
TS Amount (Rs)
149900000
TS Number
WRD/KWA-CE(NR)EST_TS/1088/2022_5_12_11
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
Jal Jeevan Mission(JJM)-JJM Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 2-Construction of 33LL Capacity Master OHSR at IDTR and 38LL Capacity GLSR at IDTR for Kaladi and Edappal Panchayaths
Edappal Sn
2
JJM Phase 3-CWSS to Edappal and adjoining Panchayaths-Site Cleaning and conducting of soil investigation of proposed GLSR site at IDTR compound near KSRTC Regional work shop, Kandanakam -investigation work-2.
Edappal Sn
3
JJM Phase 3-CWSS to Edappal and adjoining Panchayaths-Site Cleaning and conducting of soil investigation of proposed OHSR site at IDTR compound near KSRTC Regional work shop, Kandanakam -investigation work-1.
Edappal Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
12 Mar 2025
1.Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab completed. roof slab concreting completed.
Edappal Sn AE
03 Mar 2025
1.Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab completed. roof slab concreting completed.
Edappal PH Dn EE
21 Feb 2025
1.Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab completed. roof slab concreting completed.
Edappal PH Dn EE
14 Feb 2025
1.Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab completed. roof slab concreting completed.
Edappal Sn AE
12 Feb 2025
1.Soil investigation 1 - Work Completed 2. Soil investigation 2 - Work Completed 3. GLSR - plastering 4.OHSR- Tank base slab concreting completed, Haunch concrete completed, side wall concreting completed. shuttering of roof slab completed. roof slab concreting completed.