Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Dec 2023 | 4757 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
28 Dec 2023 | 4757 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
26 Dec 2023 | 4757 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
22 Dec 2023 | 4757 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
20 Dec 2023 | 4757 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
18 Dec 2023 | 4716 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
15 Dec 2023 | 4716 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
13 Dec 2023 | 4716 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
11 Dec 2023 | 4716 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM | |
08 Dec 2023 | 4716 connections completed out of 6411 FHTCs & Pipe laying works progressing | Aluva AE JJM |