Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Apr 2024 | 4865 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
17 Apr 2024 | 4865 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
15 Apr 2024 | 4865 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
08 Apr 2024 | 4865 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
05 Apr 2024 | 4865 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
03 Apr 2024 | 4865 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
01 Apr 2024 | 4847 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
30 Mar 2024 | 4847 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
27 Mar 2024 | 4847 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM | |
25 Mar 2024 | 4847 connections given out of 6411 connections. Balance connection work ongoing. Pipeline works completed. | Aluva AE JJM |