Work order-Replacing raw water pumping main

26/09/2023 | File: Karukutty-Replacing raw water pumping main.pdf | Download

LOA-Jal Jeevan Mission- Karukutty and Mookkannoor - Replacing 200mm AC Raw water Pumping main from Ezhattumugham RWPH to 4.5mld WTP at Vellappara with 300mm DI K9 pipe.

Work order- Karukutty Part 1

26/09/2023 | File: Karukutty part 1.pdf | Download

LOA-Jal Jeevan Mission (JJM)-RWSS to Karukutty & Mookkannoor -Multi Village Scheme - Extension of Pipe Line and Providing Functional House Hold Tap Connections (FHTC) to Rural House Holds in various Wards of Karukutty Panchayath and Allied Works.-Part 1

Schematic Diagram

29/12/2022 | File: Karukutty.jpg | Download

Revised Work Schedule As on 31-12-2021

04/02/2022 | File: 2nd Work Schedule Karukutty.pdf | Download

Second revised work schedule

Irrigation agreement

13/07/2021 | File: Karukutty Irgn.Agmt.pdf | Download

Irrigation NOC

13/07/2021 | File: Irrigation NOC.pdf | Download

Irrigation agreement doc.

13/07/2021 | File: irrigation Agreement.pdf | Download

TS

31/12/2020 | File: TS_KARUKUTTY.pdf | Download

TS_KARUKUTTY

AS

31/12/2020 | File: AS_JJM.pdf | Download

AS JJM