03 Feb 2024 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given | Thrissur PH Dn EE | |
13 Jan 2024 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
10 Jan 2024 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
06 Jan 2024 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
03 Jan 2024 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
30 Dec 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
26 Dec 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
23 Dec 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
22 Dec 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE | |
18 Dec 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 151 FHTCs given. | Thrissur PH Dn EE |