Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Nov 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
07 Nov 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
06 Nov 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
04 Nov 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
03 Nov 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
02 Nov 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
31 Oct 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
30 Oct 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
28 Oct 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE | |
27 Oct 2023 | WORK ONGOING ,LAYING OF DI PIPE 39% COMPLETED, 67 FHTCs given | Thrissur PH Dn EE |