| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Aug 2026 | Tank cover slab completed. Parapet work started. | Kannur WS Sn AE 2 | |
| 17 Jul 2026 | Deck slab concreting completed. Side wall 3m completed. | Kannur WS Sn AE 2 | |
| 18 Jun 2026 | Ongoing bottom main slab concreting. | Kannur WS Sn AE 2 | |
| 04 Jun 2026 | Bottom main slab Shuttering and reinforcement work completed. | Kannur WS Sn AE 2 | |
| 29 Apr 2026 | Ongoing column concrete work. | Kannur WS Sn AE 2 | |
| 17 Apr 2026 | Ongoing column concrete work. | Kannur WS Sn AE 2 | |
| 08 Apr 2026 | Ongoing column concrete work. | Kannur WS Sn AE 2 | |
| 24 Mar 2026 | Ongoing column concrete work. | Kannur WS Sn AE 2 | |
| 06 Mar 2026 | Ongoing column concrete work. | Kannur WS Sn AE 2 | |
| 25 Feb 2026 | Plinth beam work completed. | Kannur WS Sn AE 2 |