| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Feb 2026 | Plinth beam work completed. | Kannur WS Sn AE 2 | |
| 11 Feb 2026 | PCC Work of the footing completed. | Kannur WS Sn AE 2 | |
| 06 Feb 2026 | PCC Work of the footing completed. | Kannur WS Sn AE 2 | |
| 20 Jan 2026 | PCC Work of the footing completed | Kannur WS Sn AE 2 | |
| 12 Jan 2026 | Old GLSR Tank Chalakkunnu - Demolished, New tank structural drawing submitted for approval. | Kannur PH Dn EE | |
| 05 Jan 2026 | Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval. | Kannur WS Sn AE 2 | |
| 30 Dec 2025 | Old GLSR Tank Chalakkunnu - Demolished,New tank structural drawing submitted for approval. | Kannur WS Sn AE 2 | |
| 07 Mar 2025 | TS to be issued | Kannur PH Dn EE | |
| 25 Feb 2025 | TS to be issued | Kannur PH Dn EE | |
| 19 Feb 2025 | TS to be issued | Kannur PH Dn EE |