Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Mar 2023 WTP-COMMISIONED ON 07.01.20202 WORK COMPLETED ON 15.11.2022 Chittur Project Dn - AE 4
13 Mar 2023 work completed Chittur Project Dn - AE 4
09 Mar 2023 Work in progress | 98% Completed | 09/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
05 Mar 2023 Work in progress | 98% Completed | 05/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
24 Feb 2023 Work in progress | 98% Completed | 24/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
17 Feb 2023 Work in progress | 98% Completed | 17/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
10 Feb 2023 Work in progress | 98% Completed | 10/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
03 Feb 2023 Work in progress | 98% Completed | 03/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
30 Jan 2023 Work in progress | 98% Completed | 30/01/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4
20 Jan 2023 Work in progress | 98% Completed | 20/01/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done Chittur Project Dn - AE 4