Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Mar 2023 | WTP-COMMISIONED ON 07.01.20202 WORK COMPLETED ON 15.11.2022 | Chittur Project Dn - AE 4 | |
13 Mar 2023 | work completed | Chittur Project Dn - AE 4 | |
09 Mar 2023 | Work in progress | 98% Completed | 09/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
05 Mar 2023 | Work in progress | 98% Completed | 05/03/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
24 Feb 2023 | Work in progress | 98% Completed | 24/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
17 Feb 2023 | Work in progress | 98% Completed | 17/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
10 Feb 2023 | Work in progress | 98% Completed | 10/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
03 Feb 2023 | Work in progress | 98% Completed | 03/02/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
30 Jan 2023 | Work in progress | 98% Completed | 30/01/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 | |
20 Jan 2023 | Work in progress | 98% Completed | 20/01/2023 pack-1 -bitumen indent requirement letter submitted to PWD , Road restoration work to be done | Chittur Project Dn - AE 4 |