Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2024 | Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M | Palakkad Proj AE 3 | |
27 Jun 2024 | Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M | Palakkad Proj AE 3 | |
26 Jun 2024 | Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 402M. Total laid-456M | Palakkad Proj AE 3 | |
25 Jun 2024 | Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 282M. Total laid-336M | Palakkad Proj AE 3 | |
22 Jun 2024 | Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 102M. Total laid-156M | Palakkad Proj AE 3 | |
20 Jun 2024 | Laying started.90mm PN 8 - 54M laid. | Palakkad Proj AE 3 | |
20 Jun 2024 | 25 May 2024 Laying started.90mm PN 8 - 54M laid. | Palakkad Proj AE 3 | |
25 May 2024 | Laying started.90mm PN 8 - 54M laid. | Palakkad Project Dn EE | |
18 May 2024 | Laying started.90mm PN 8 - 54M laid. | Palakkad Proj AE 3 | |