| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jan 2025 | Estimate Submitted for TS | Thalassery PH Sn AE | |
| 13 Jan 2025 | Estimate Submitted for TS | Thalassery PH Sn AE | |
| 03 Jan 2025 | Estimate Submitted for TS | Thalassery PH Sn AE | |
| 18 Dec 2024 | Estimate Submitted for TS | Thalassery PH Sn AE | |
| 02 Dec 2024 | TS to be accorded | Kannur PH Dn EE | |
| 19 Nov 2024 | TS to be accorded | Kannur PH Dn EE | |
| 04 Nov 2024 | AS Accorded on 21-10-2024. | Kannur PH Dn EE |