| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Mar 2026 | Agreement executed | Thalassery PH Sn AE | |
| 23 Feb 2026 | Agreement executed | Thalassery PH Sn AE | |
| 18 Feb 2026 | Agreement executed | Thalassery PH Sn AE | |
| 09 Feb 2026 | Agreement executed | Thalassery PH Sn AE | |
| 29 Jan 2026 | Agreement executed | Thalassery PH Sn AE | |
| 19 Jan 2026 | Agreement executed | Thalassery PH Sn AE | |
| 08 Jan 2026 | Agreement executed | Thalassery PH Sn AE | |
| 05 Jan 2026 | Agreement executed | Thalassery PH Sn AE | |
| 24 Dec 2025 | Agreement executed | Thalassery PH Sn AE | |
| 17 Dec 2025 | Agreement executed | Thalassery PH Sn AE |