Status Date Overall Project Status Project Officer Contact
01 Jul 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. 271 FHTCs provided. FHTCs tagging progressing Thrissur PH Dn EE
27 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. 256 FHTCs provided. Thrissur PH Dn EE
26 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. FHTCs tagging on progress. 251 FHTCs provided Thrissur PH Dn EE
24 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. FHTCs tagging on progress. 246 FHTCs provided Thrissur PH Dn EE
23 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying.FHTCs tagging on progress. 231 FHTCs provided Thrissur PH Dn EE
22 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. FHTCs tagging on progress. 221 FHTCs provided Thrissur PH Dn EE
21 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying completed about 50%. FHTCs tagging on progress. 201 FHTCs provided Thrissur PH Dn EE
20 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying completed about 50%. FHTCs tagging on progress. 191 FHTCs provided Thrissur PH Dn EE
19 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying and tagging on progress. laying completed about 50%. FHTCs tagging on progress. 191 FHTCs provided Thrissur PH Dn EE
17 Jun 2023 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying and tagging on progress. laying completed about 50%. FHTCs tagging on progress. 191 FHTCs provided Thrissur PH Dn EE