Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jul 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. 271 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
27 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. 256 FHTCs provided. | Thrissur PH Dn EE | |
26 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. FHTCs tagging on progress. 251 FHTCs provided | Thrissur PH Dn EE | |
24 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying. FHTCs tagging on progress. 246 FHTCs provided | Thrissur PH Dn EE | |
23 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. Pipe laying.FHTCs tagging on progress. 231 FHTCs provided | Thrissur PH Dn EE | |
22 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. FHTCs tagging on progress. 221 FHTCs provided | Thrissur PH Dn EE | |
21 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying completed about 50%. FHTCs tagging on progress. 201 FHTCs provided | Thrissur PH Dn EE | |
20 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying completed about 50%. FHTCs tagging on progress. 191 FHTCs provided | Thrissur PH Dn EE | |
19 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying and tagging on progress. laying completed about 50%. FHTCs tagging on progress. 191 FHTCs provided | Thrissur PH Dn EE | |
17 Jun 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing pipe laying and tagging on progress. laying completed about 50%. FHTCs tagging on progress. 191 FHTCs provided | Thrissur PH Dn EE |