Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 424 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
14 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 419 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
11 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 409 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
10 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 409 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
09 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 404 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
08 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 404 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
07 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 404 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
05 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 391 FHTCs provided. FHTCs tagging progressing | Thrissur PH Dn EE | |
04 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 391 FHTCs provided. FHTCs tagging progressing. | Thrissur PH Dn EE | |
03 Aug 2023 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. work ongoing. 391 FHTCs provided. FHTCs tagging progressing. | Thrissur PH Dn EE |