Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Nov 2022 Offer Received and Selection Notice Issued Chavara AE
25 Nov 2022 Offer Received and Selection Notice Issued Chavara AE
24 Nov 2022 Single offer recieved at PH Division Kollam were sanctioned vide proceedings No: DB2/3014/DW/IRE//PHDNK/2022 Dated: 09.11.2022 and submitted to Sub Div for further action Chavara AE
22 Nov 2022 Single offer recieved at PH Division Kollam were sanctioned vide proceedings No: DB2/3014/DW/IRE//PHDNK/2022 Dated: 09.11.2022 and submitted to Sub Div for further action Kollam PH Dn EE
21 Nov 2022 Retender opened on 30.09.22. Single offer received submitted to division. Chavara AE
15 Nov 2022 Retender opened on 30.09.22. Single offer received submitted to division. Chavara AE
11 Nov 2022 Retender opened on 30.09.22. Single offer received submitted to division. Chavara AE
07 Nov 2022 Retender opened on 30.09.22. Single offer received submitted to division. Chavara AE
02 Nov 2022 Retender opened on 30.09.22. Single offer received submitted to division. Kollam PH Dn EE
31 Oct 2022 Retender opened on 30.09.22. Single offer received submitted to division. Chavara AE