| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 30 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Kollam PH Dn EE | |
| 28 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 24 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 21 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 18 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 14 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 10 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 07 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE | |
| 04 Mar 2023 | Agreement executed On 14.12.2022, Material supply order issued, work started | Chavara AE |