Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2024 | 42700 M PVC & 50M DI Pipes Laid, GI Gap & Interconnections ongoing. 1011 FHTCs Provided. 940 geotagged. | Pullad PH Sn - AE | |
21 Jun 2024 | 42700 M PVC & 50M DI Pipes Laid, GI Gap & Interconnections ongoing. Approximate 1011 FHTCs Provided. 940 geotagged. | Pullad PH Sn - AE | |
18 Jun 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. Approximate 1011 FHTCs Provided. 940 geotagged. | Pullad PH Sn - AE | |
13 Jun 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. Approximate 1011 FHTCs Provided. 940 geotagged. | Pullad PH Sn - AE | |
11 Jun 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. Approximate 900 FHTCs Provided. 790 geotagged. | Pullad PH Sn - AE | |
07 Jun 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. Approximate 900 FHTCs Provided. 790 geotagged. | Pullad PH Sn - AE | |
30 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. 830 FHTCs Provided. 634 geotagged. | Pullad PH Sn - AE | |
25 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. 830 FHTCs Provided. 634 geotagged. | Pullad PH Sn - AE | |
21 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections ongoing. 830 FHTCs Provided. 634 geotagged. | Pullad PH Sn - AE | |
17 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. | Pullad PH Sn - AE |