Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. Pullad PH Sn - AE
06 May 2024 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. Pullad PH Sn - AE
02 May 2024 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. Pullad PH Sn - AE
27 Apr 2024 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. Pullad PH Sn - AE
23 Apr 2024 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. Pullad PH Sn - AE
19 Apr 2024 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged Pullad PH Sn - AE
16 Apr 2024 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged Pullad PH Sn - AE
11 Apr 2024 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged Pullad PH Sn - AE
06 Apr 2024 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged Pullad PH Sn - AE
01 Apr 2024 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged Pullad PH Sn - AE