13 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. | Pullad PH Sn - AE | |
06 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. | Pullad PH Sn - AE | |
02 May 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. | Pullad PH Sn - AE | |
27 Apr 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. | Pullad PH Sn - AE | |
23 Apr 2024 | 42700 M PVC & 50M DI Pipes Laid, Gap & Interconnections provided. 750 FHTCs Provided. 600 geotagged. | Pullad PH Sn - AE | |
19 Apr 2024 | 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged | Pullad PH Sn - AE | |
16 Apr 2024 | 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged | Pullad PH Sn - AE | |
11 Apr 2024 | 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged | Pullad PH Sn - AE | |
06 Apr 2024 | 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged | Pullad PH Sn - AE | |
01 Apr 2024 | 42700 M PVC & 50MDI Pipes Laid. 570 FHTCs Provided. 532 geotagged | Pullad PH Sn - AE |