Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Feb 2022 |
Delay in getting PWD sanction and RE. As the scheduled quantity of pipe for providing FHTC and branch road in the work are very less to complete the work additional work arranged. 10902m 90mm PVC 5440m 110mm PVC,120m 100mm GI and 340m 80mm GI pipes laid,63mm PVC laying work in progress,Total 1673 FHTCs Provided. |
Kaduthuruthy Dn EE |
|
09 Feb 2022 |
Delay in getting PWD sanction and RE. As the scheduled quantity of pipe for providing FHTC and branch road in the work are very less to complete the work additional work arranged.
10902m 90mm PVC 5440m 110mm PVC,120m 100mm GI and 340m 80mm GI pipes laid,63mm PVC laying work in progress,Total 1673 FHTCs Provided. |
Kaduthuruthy Dn EE |
|
08 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
07 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
06 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
05 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
04 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
03 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
02 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
31 Jan 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|