Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
19 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
18 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
17 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
16 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
15 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
14 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
13 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
12 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
11 Feb 2022 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|