| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 622Nos FHTCs provided. | Chalakudy AE 2 | |
| 13 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 601Nos FHTCs provided. | Chalakudy AE 2 | |
| 09 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 601Nos FHTCs provided. | Chalakudy AE 2 | |
| 07 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 586Nos FHTCs provided. | Chalakudy AE 2 | |
| 06 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 568Nos FHTCs provided. | Chalakudy AE 2 | |
| 02 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 552Nos FHTCs provided. | Chalakudy AE 2 | |
| 01 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 552Nos FHTCs provided. | Chalakudy AE 2 | |
| 27 Aug 2021 | 200 mm DI PIPE Laying 90%Work completed, 552Nos FHTCs provided. | Chalakudy AE 2 | |
| 26 Aug 2021 | cc IV th and part bill submitted | Chalakudy AE 2 | |
| 25 Aug 2021 | 200 mm DI PIPE Laying 90%Work completed, 529Nos FHTCs provided. | Chalakudy AE 2 |