| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Dec 2021 | 200 mm DI PIPE Laying 94%Work completed, 1246 Nos FHTCs provided. | Chalakudy AE 2 | |
| 02 Dec 2021 | 200 mm DI PIPE Laying 94%Work completed, 1246 Nos FHTCs provided. | Chalakudy AE 2 | |
| 30 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1192Nos FHTCs provided. | Chalakudy AE 2 | |
| 29 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1134Nos FHTCs provided. | Chalakudy AE 2 | |
| 27 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1094Nos FHTCs provided. | Chalakudy AE 2 | |
| 26 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1094Nos FHTCs provided. | Chalakudy AE 2 | |
| 25 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1094Nos FHTCs provided. | Chalakudy AE 2 | |
| 24 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1094Nos FHTCs provided. | Chalakudy AE 2 | |
| 23 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1054Nos FHTCs provided. | Chalakudy AE 2 | |
| 22 Nov 2021 | 200 mm DI PIPE Laying 94%Work completed, 1053Nos FHTCs provided. | Chalakudy AE 2 |