| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 18 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 16 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 12 Oct 2021 | 200 mm DI PIPE Laying 91%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 07 Oct 2021 | 200 mm DI PIPE Laying 90%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 05 Oct 2021 | 200 mm DI PIPE Laying 90%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 04 Oct 2021 | 200 mm DI PIPE Laying 90%Work completed, 682Nos FHTCs provided. | Chalakudy AE 2 | |
| 29 Sep 2021 | 200 mm DI PIPE laying work 90% completed, 645Nos FHTCs provided. CC V th & part bill submitted to Sub Division on 28.09.2021 | Chalakudy AE 2 | |
| 18 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 645Nos FHTCs provided. | Chalakudy AE 2 | |
| 17 Sep 2021 | 200 mm DI PIPE Laying 90%Work completed, 633Nos FHTCs provided. | Chalakudy AE 2 |