Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Apr 2026 Measurement recorded .Bill submitted Kottiyam PH Sn AE
29 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed. Cholorination tank has been placed at Kalluvettamkuzhi, Thattarkonam and Thazhampana Pumphouses. Measurements Recorded. Kottiyam PH Sn AE
26 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed. Cholorination tank has been placed at Kalluvettamkuzhi, Thattarkonam and Thazhampana Pumphouses. Measurement Recorded. Kottiyam PH Sn AE
23 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed at Kalluvettamkuzhi and Thattarkonam Pumphouse Kottiyam PH Sn AE
19 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed at Kalluvettamkuzhi and Thattarkonam Pumphouse Kottiyam PH Sn AE
16 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed at Kalluvettamkuzhi and Thattarkonam Pumphouse Kottiyam PH Sn AE
13 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed at Kalluvettamkuzhi and Thattarkonam Pumphouse Kottiyam PH Sn AE
10 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed at Kalluvettamkuzhi and Thattarkonam Pumphouse Kottiyam PH Sn AE
07 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed at Kalluvettamkuzhi and Thattarkonam Pumphouse Kottiyam PH Sn AE
05 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed. Kottiyam PH Sn AE