Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Mar 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed. Kottiyam PH Sn AE
27 Feb 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed. Kottiyam PH Sn AE
24 Feb 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed. Kottiyam PH Sn AE
21 Feb 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed.Cholorination tank has been placed. Kottiyam PH Sn AE
16 Feb 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed. Kottiyam PH Sn AE
13 Feb 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work and painting work completed. Kottiyam PH Sn AE
10 Feb 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thattarkonam Pump house-Demolishing brick work, RR work, Brick work and plastering work completed. Kottiyam PH Sn AE
31 Jan 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thttarkonam Pump house-Demolishing brick work completed and RR work completed Kottiyam PH Sn AE
27 Jan 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed.Thttarkonam Pump house-Demolishing brick work completed. Kottiyam PH Sn AE
22 Jan 2026 Kalluvettankuzhy pump house- Demolishing and dismantling work completed, Brick work completed.Plastering work completed . Thazhampana Pump house- RR work completed. Brick work completed. Plastering work completed,Roof work completed Kottiyam PH Sn AE