Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Jan 2024 | All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1987.1m/2000m) and 160mm 10kg pvc rider line(2853.05m/3200m) pipe laying in progress. | Kollam Project Dn EE | |
09 Jan 2024 | All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2627.45m/3200m) pipe laying in progress. | Kollam Project HD | |
08 Jan 2024 | All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1961.8m/2000m) and 160mm 10kg pvc rider line(2626.45m/3200m) pipe laying in progress. | Kollam Project HD | |
07 Jan 2024 | All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1957.85m/2000m) and 160mm 10kg pvc rider line(2621.85m/3200m) pipe laying in progress. | Kollam Project HD | |
05 Jan 2024 | All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI(1928.2m/2000m) and 160mm 10kg pvc rider line(2587.85m/3200m) pipe laying in progress. | Kollam Project HD | |
05 Dec 2023 | All structural works upto roof slab level completed. OHSR plastering works in progress. 300mm DI and 160mm 10kg pvc rider line pipe laying in progress. | Kollam Project Dn EE | |
04 Dec 2023 | Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering works in progress. Valve chamber concreting works completed. 300mm DI and 160mm 10kg pvc rider line pipe laying in progress. | Kollam Project Dn EE | |
03 Dec 2023 | Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering works in progress | Kollam Project Dn EE | |
02 Dec 2023 | Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering works in progress | Kollam Project Dn EE | |
01 Dec 2023 | Total pipe laid length 1378.10m.Total no of household connections provided 67nos. Earth work excavation for 8 no footing completed on 22/07/2023,PCC bed completed on 25/07/2023 and Reinforcement work and footing work for 8 nos footing completed on 28/07/2023.column concrete for 8 nos completed on 1/08/2023 and deshuttering and curing done. Earth work excavation done for another 8 nos of footing on 5/08/2023 and footing PCC works completed on 6/08/2023.Balance footing RCC works completed on 8/08/2023 and curing for balance footing done on 9/08/2023.Shuttering work completed on 10/08/2023. Balance Column concrete completed on 11/08/2023 and deshuttering and curing done on 12/08/2023.Levelling for pcc completed on 13/08/2023.Plinth beam PCC work started on 14/08/2023.Plinth beam shuttering completed on 16/08/2023.plinth beam concrete work completed on 17/08/2023.deshuttering completed and shoe concrete and column reinforcement for 10 nos of column work completed on 18/08/2023.concrete work completed for 10 nos of column on 19/08/2023.curing for 10 nos of column with gunny bags is progressing. Column shuttering for balance column and concreting done. Stair concrete completed on 22/08/2023.brace beam-reinforcement work completed on 25/8/2023.Brace beam concrete completed on 27/8/2023.column reinforcement work and shuttering above brace beam done on 1/09/2023.10 numbers of column concrete above first brace beam done on 2/09/2023.Reinforcement work for balance 6 column above first brace beam done on 03/09/2023 and their column concrete (6nos) completed on 4/09/2023.stair concrete work completed for third flight. Second brace beam bottom setting completed on 8/09/2023.second brace beam reinforcement work and shuttering work completed on 11/09/2023.Second brace beam concrete completed on 12/09/2023.8 nos column concrete above second brace beam completed on 14/09/2023.balance 8 nos column concrete above second brace beam completed on 16/09/2023.Floor beam bottom setting done on 19/09/2023.Floor slab side shuttering done on 20/09/2023. Side shuttering of floor beam completed on 21/09/2023.Floor slab shuttering done on 23/09/2023.Total pipe laid length 1378.10m.Total no of household connections provided 84 nos.200mm DI vertical pipe (Scour&overflow)installed.Floor beam concrete work completed on 11/10/2023.Floor slab reinforcement work completed on 14/10/2023.Side wall reinforcement work on progressing.Floor slab concrete completed on 17/10/2023.Column shuttering & reinforcement work above floor slab completed on 19/10/2023.Column concrete above floor slab completed on 20/10/2023.Remaining column concrete above floor slab completed on 24/10/2023.Haunch concrete completed on 28/10/20223. Haunch deshuttering done on 29/10/2023.Sidewall concrete completed on 31/10/2023 and curing done on 1/11/2023.Side wall reinforcement work and outer shuttering of first lift done on 3/11/2023.Sidewall supporting and platform setting done on 5/11/2023. Sidewall 2nd lift concrete work completed on 6/11/2023. Sidewall reinforcement work of 3rd flight done on 8/11/2023.Inside shuttering almost done on 9/11/2023.Shutter supporting of platform setting done on 10/11/2023.Sidewall concrete work ( 3rd lift )completed on 11/11/2023.Outside shuttering completed on 15/11/2023.Sidewall concrete work(4th lift) completed on 17/11/2023. Deshuttering completed on 18/11/2023. Roof slab concreting completed . curing for roof slab in progress . OHSR plastering work started | Kollam Project Dn EE |