Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Feb 2024 | 3181 no FHTCs given, Pipe laying completed. Contractor submitted final bill since there is no more connection to be provided in the village under this work | Shornur PH Dn EE | |
27 Dec 2022 | 3178 no FHTCs given, Pipe laying completed. | Shornur PH Dn EE | |
23 Nov 2022 | Nellaya Phase I work 3908 FHTCs out of 4167 FHTCs given, 3668 nos geo tagged done. And additional work completed. | Shornur PH Dn EE | |
11 Oct 2022 | Additional pipe line work 6 km arranged to facilitate balance FHTC | Shoranur PH Sub Dn AEE | |
22 Jun 2022 | 70% of work completed. 2917 FHTCs out of 4167 FHTCs given. Work in progress. | Shornur PH Dn EE | |
05 Apr 2022 | 68% of work completed. 2871 FHTCs out of 4167 FHTCs given. Work in progress. | Shornur PH Dn EE | |
14 Mar 2022 | 2792 FHTCs out of 4167 FHTCs given. Work in progress. | Shornur PH Dn EE | |
19 Feb 2022 | 70% of work completed. 2921 FHTCs out of 4167 FHTCs given. Work in progress. | Shoranur PH Sub Dn AEE | |
19 Feb 2022 | 62% of work completed. 2619 FHTCs out of 4167 FHTCs given. Work in progress. | Shornur PH Dn EE | |
15 Feb 2022 | 62% of work completed. 2610 FHTCs out of 4167 FHTCs given. Work in progress. | Shornur PH Dn EE |