| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Nov 2022 | Work on going | Painavu PH Section AE | |
| 16 Nov 2022 | Pipe supply done, work started | Painavu PH Section AE | |
| 03 Oct 2022 | Agreement executed, pipe supply not done | Painavu PH Section AE | |
| 20 Sep 2022 | Agreement executed, pipe supply not done | Painavu PH Section AE | |
| 17 Sep 2022 | Agreement executed | Painavu PH Section AE | |
| 13 Sep 2022 | work order issued | Painavu PH Section AE | |
| 01 Sep 2022 | work Order issued | Painavu PH Section AE | |
| 01 Sep 2022 | work Tendered | Painavu PH Section AE | |
| 27 Aug 2022 | Work Order Issued | Thodupuzha PH Dn EE |