| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jun 2023 | CC 1st & Final Bill Submitted | Painavu PH Section AE | |
| 31 Mar 2023 | Work Completed, Bill under Preparation . | Painavu PH Section AE | |
| 27 Mar 2023 | Pipe Laying Completed. Line Charges. Since all houses around the pipe line is having consumer connections, we could not able to find new connection as mentioned in the work. Work can be marked as completed with since pipe laying is completed | Painavu PH Section AE | |
| 23 Mar 2023 | Line Charging work in progress | Painavu PH Section AE | |
| 13 Mar 2023 | Pipe Laying Works completed | Painavu PH Section AE | |
| 08 Mar 2023 | Pipe Laying Works going on | Painavu PH Section AE | |
| 27 Feb 2023 | Pipe Laying works in progress | Painavu PH Section AE | |
| 21 Feb 2023 | Pipe Laying Works going on | Painavu PH Section AE | |
| 14 Feb 2023 | Pipe Laying Works going on | Painavu PH Section AE | |
| 06 Feb 2023 | Pipe Laying started | Painavu PH Section AE |