28 Feb 2024 Civil work of sump, pump house, filter bed & filter house, wash water tank, clarifier & flocculator work, aerator, solution tanks, office room, Kizhakkanmala & Pazhamala OHSRs are completed. Renovotion of Mylachal Dalumukham GLSRs are completed. excepting PWD roads pipe laying works are completed. Thiruvananthapuram Project AE2
24 Jan 2023 RCC of roof slab of sump completed. 50 % of compound wall construction completed. Earth work of filter house is progressing. Transmission main and pumping main pipe line works progressing Thiruvananthapuram Project AE1
13 Sep 2022 Site clearance is going on .Inauguration of the project conducted on 29 .08.2022 Thiruvananthapuram Project AE1
19 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1
12 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1
08 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1
04 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1
01 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1
20 Jul 2022 Work order issued to the firm is cancelled by the SE ,PH Circle ;Thiruvananthapuram vide Order No.KWA/PHC/D2/8/2018 Dated 06.05.2022 and the work is retendered Thiruvananthapuram Project AE1
17 Jul 2022 Work order issued to the firm is cancelled by the SE ,PH Circle ;Thiruvananthapuram vide Order No.KWA/PHC/D2/8/2018 Dated 06.05.2022 Thiruvananthapuram Project AE1