Kizhakkanmala Water Supply Scheme

Project Kizhakkanmala Water Supply Scheme
Project Code TVMKIIFB0919697
Type Main project
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB - Kizhakkanmala Water Supply Scheme - water Supply project to Aryancode and Perumkadavila Panchayaths.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 430900000
AS Number Order no WRD025-28/APR-6/2019/KIIFB dated 07/09/19
TS Amount (Rs) 403400000
TS Number TS/2021-22/2020/24358 Dated 10/05/2021
Total Bill Submitted (Rs) 214000
Total Bill Paid (Rs) 214000
Population Benefitted 99785
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Aryancode and Perumkadavila panchayaths.
Work Plan Download

Packages

No. Project Name Location View
1 Kizhakkanmala Water Supply Scheme Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Feb 2024 Civil work of sump, pump house, filter bed & filter house, wash water tank, clarifier & flocculator work, aerator, solution tanks, office room, Kizhakkanmala & Pazhamala OHSRs are completed. Renovotion of Mylachal Dalumukham GLSRs are completed. excepting PWD roads pipe laying works are completed. Thiruvananthapuram Project AE2
24 Jan 2023 RCC of roof slab of sump completed. 50 % of compound wall construction completed. Earth work of filter house is progressing. Transmission main and pumping main pipe line works progressing Thiruvananthapuram Project AE1
13 Sep 2022 Site clearance is going on .Inauguration of the project conducted on 29 .08.2022 Thiruvananthapuram Project AE1
19 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1
12 Aug 2022 Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 Thiruvananthapuram Project AE1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 30/06/2022

Processing Dates

AS Date 07 Sep 2019
TS Date 10 May 2021

Other details