Project | Kizhakkanmala Water Supply Scheme |
---|---|
Project Code | TVMKIIFB0919697 |
Type | Main project |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB - Kizhakkanmala Water Supply Scheme - water Supply project to Aryancode and Perumkadavila Panchayaths. |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
AS Amount (Rs) | 430900000 |
AS Number | Order no WRD025-28/APR-6/2019/KIIFB dated 07/09/19 |
TS Amount (Rs) | 403400000 |
TS Number | TS/2021-22/2020/24358 Dated 10/05/2021 |
Total Bill Submitted (Rs) | 214000 |
Total Bill Paid (Rs) | 214000 |
Population Benefitted | 99785 |
Capacity in MLD | 10.00 |
Actual Project Completion Date | Date is not specified |
Coverage | Aryancode and Perumkadavila panchayaths. |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Feb 2024 | Civil work of sump, pump house, filter bed & filter house, wash water tank, clarifier & flocculator work, aerator, solution tanks, office room, Kizhakkanmala & Pazhamala OHSRs are completed. Renovotion of Mylachal Dalumukham GLSRs are completed. excepting PWD roads pipe laying works are completed. | Thiruvananthapuram Project AE2 | |
24 Jan 2023 | RCC of roof slab of sump completed. 50 % of compound wall construction completed. Earth work of filter house is progressing. Transmission main and pumping main pipe line works progressing | Thiruvananthapuram Project AE1 | |
13 Sep 2022 | Site clearance is going on .Inauguration of the project conducted on 29 .08.2022 | Thiruvananthapuram Project AE1 | |
19 Aug 2022 | Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 | Thiruvananthapuram Project AE1 | |
12 Aug 2022 | Work order issued to the firm M/s Chicago Constructions International Pvt Ltd; Thiruvananthapuram on 22.07.2022 | Thiruvananthapuram Project AE1 |
Date of start of Project | Date is not specified |
---|---|
Scheduled date of Completion of the Project | Date is not specified |
Expected date of Completion | 30/06/2022 |
AS Date | 07 Sep 2019 |
---|---|
TS Date | 10 May 2021 |
Project Officers | View |
---|