Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Mar 2024 | 1380 m 90 mm UPVC pipe laid so far.Laying works on going. | Palakkad Project Dn AE 4 | |
09 Mar 2024 | 1152 m 90 mm UPVC pipe laid so far.Laying works on going. | Palakkad Project Dn AE 4 | |
08 Mar 2024 | 906 m 90 mm UPVC pipe laid so far.Laying works on going. | Palakkad Project Dn AE 4 | |
07 Mar 2024 | 600 m 90 mm UPVC pipe laid so far.Laying works on going. | Palakkad Project Dn AE 4 | |
06 Mar 2024 | 90 mm UPVC 330 m laid in Panamanna - Ambalavattom road ration shop junction. | Palakkad Project Dn AE 4 | |
02 Mar 2024 | Suppled 584 nos (3504 mtrs) of 6 mtr 90mm 6 kg AIZAR ISI. | Palakkad Project Dn AE 4 | |
02 Mar 2024 | INVOICE No : GP050620 date - 02/03/2024 90mm 6kg AIZAR ISI - 6 mtr. Purchased 3504 mts of pipe. | Palakkad Project Dn AE 4 | |
02 Mar 2024 | 90 MM 6 KG AIZAR ISI - 6 MTR Pipe. 3504 mts(584 nos) has been purchased. | Palakkad Project Dn AE 4 |