Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Jun 2024 | Total laid so far = 3.987/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
21 Jun 2024 | Total laid so far = 3.366/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
18 Jun 2024 | Total laid so far = 3.366/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
15 Jun 2024 | Total laid so far = 3.366/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
11 Jun 2024 | Total laid so far = 3.366/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
08 Jun 2024 | Total laid so far = 3.366/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
06 Jun 2024 | Total laid so far = 2.871/11km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
04 Jun 2024 | Total laid so far 90 mm UPVC = 2.837 kms. Vaniamkulam - kothakkurssi road btw ( n16 n17 ) near pathamkulam puthuvayil colony road 90 mm UPVC class - 3/6 kg pipe = 42 m 80 mm GI pipe ( Culvert crossing ) = 6 m | Palakkad Proj Dn AE 4 | |
03 Jun 2024 | Total laid so far = 2.795km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 | |
01 Jun 2024 | Total laid so far = 2.795km.Interconnection work and restoration work on going. | Palakkad Project Dn AE 4 |