| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Mar 2026 | Work started.750 meter pipe laid. awaiting road cutting permission | Kannur WS Sn AE 2 | |
| 25 Feb 2026 | Work started.750 meter pipe laid. | Kannur WS Sn AE 2 | |
| 16 Feb 2026 | Work started.750 meter pipe laid. | Kannur WS Sn AE 2 | |
| 09 Feb 2026 | Work started.750 meter pipe laid. | Kannur WS Sn AE 2 |