Status Date Overall Project Status Project Officer Contact
25 Sep 2026 Work started.750 meter pipe laid. MOU regarding contonment land from contonment board pending Kannur WS Sn AE 2
14 Aug 2026 Work started.750 meter pipe laid. MOU regarding contonment land from contonment board pending Kannur WS Sn AE 2
17 Jul 2026 Work started.750 meter pipe laid. MOU regarding contonment land from contonment board pending. Kannur WS Sn AE 2
07 Jul 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2
18 Jun 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2
04 Jun 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2
29 Apr 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2
17 Apr 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2
08 Apr 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2
24 Mar 2026 Work started.750 meter pipe laid. awaiting road cutting permission Kannur WS Sn AE 2