| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Apr 2024 | Road Restoration GI Gap Works | Kadakkal PH Sn - AE | |
| 12 Apr 2024 | GI Gap Works | Kadakkal PH Sn - AE | |
| 11 Apr 2024 | GI Gap Works | Kadakkal PH Sn - AE | |
| 09 Apr 2024 | GI Gap Works | Kadakkal PH Sn - AE | |
| 08 Apr 2024 | PVC Pipe Laying | Kadakkal PH Sn - AE | |
| 30 Mar 2024 | Road Restoration | Kadakkal PH Sn - AE | |
| 04 Mar 2024 | Anchor Block Work Road Restoration | Kadakkal PH Sn - AE | |
| 17 Sep 2022 | Pipe line laying and oroviding FHTC work progressing .Construction of OHSR will start on 25/09/2022. | Kottarakkara PH Dn EE | |
| 30 May 2022 | FHTC work started | Kadakkal PH Sn - AE | |
| 21 Mar 2022 | Selection Notice issued. | Kottarakkara PH Dn EE |